On September 2, 2024, the Nuclear Safety Authority granted EDF the authorization for divergence operations at the Flamanville 3 reactor. Teams at the plant have started activities to produce the reactor's first nuclear reaction.
Following reactor loading last May, the Flamanville EPR team conducted technical tests and prepared the facilities for nuclear fission. Divergence will establish a stable nuclear reaction at 0.2% of the reactor's rated power.
A testing program will increase the power level to 25%, allowing the Flamanville EPR to connect to the national electricity grid by late autumn 2024. Testing will continue for several months as reactor power is gradually increased.
R. P.
Copyright © 2024 FinanzWire, all reproduction and representation rights reserved.
Disclaimer: although drawn from the best sources, the information and analyzes disseminated by FinanzWire are provided for informational purposes only and in no way constitute an incentive to take a position on the financial markets.
Click here to consult the press release on which this article is based